Stage floor construction steps

The first step is to prepare these paving before laying the wooden floor in the basketball hall: 1. Remove dirt (dust and sand) from the surface of the base layer, otherwise it will affect the sticking of the wood floor. 2. Test the ground level, meet the installation requirements, and select the required wooden keel. Anti-corrosion and fire retardant coating spare. 3. Avoid cross construction and choose a suitable construction date. 4. Check whether the construction equipment is complete.
The second step is to lay the keel, and lay the keel and shock-absorbing pad according to the site requirements. The combination of keel and keel, keel and shock-absorbing pad should meet the actual requirements and be fixed with steel nails. And test the keel level.
The third step, laying the splint: European pine board is selected for the splint. Compared with the Xuantong multi-layer board, the environmental protection standard explains that it is durable and has good flatness. The end of the splint falls on the keel and does not hang. Staggered, the splint gap is uniform, the splint surface is smooth, and the splint gap should not be too large.
Sports wood floor structure
The fourth step, laying the moisture-proof film: The moisture-proof film is laid according to the design requirements, and there must be no folding or cracking in the middle. Use waterproof tape to stick the two layers of moisture-proof film on the plywood.
Step 5: Lay the panels and baseboards: Lay the panels and joists vertically. During the laying process, the joints of adjacent floors should be staggered, and there should be an even gap between the floors. Both sides of the floor should be fixed with steel nails, not too tight, so as not to damage the floor and edges. If the panels need to be cut, make sure the cuts are smooth and tidy, with a burr-free appearance, and the baseboards should be solid wood interior corners, secured with steel nails and the floor.
The sixth step, floor marking: Select the special marking paint for environmental protection sports floor, mark on site according to the design requirements, and clean the site after the paint is dry.
Part 7, Acceptance is completed: After the basketball hall wooden floor is installed, ensure that the acceptance is qualified, check whether there is obvious color difference on the surface, whether there is abnormal noise when walking on the floor, whether the size of the expansion joint is qualified, etc.