Construction conditions of sports wooden floor in basketball hall

1. Construction conditions
(1) Before the construction of the physical sports wooden floor, the civil engineering shall be completed and the site shall be cleaned up to meet the design requirements of the architectural drawings.
(2) After the installation of indoor water, electricity, steam, ventilation, etc. is completed, the water network pipes shall undergo a pressure test.
(3) The interior decoration roof, ultrasonic, electroacoustic, lighting and other projects are completed.
(4) The ground humidity and equilibrium moisture content are consistent with the outside world.
Sports wood floor structure
2. Construction preparation
(1) Construction tools and instruments are ready.
(2) Construction materials should be transported to designated locations and stored according to product characteristics.
(3) Inspection of construction conditions, and record the items that do not meet the construction requirements.
(4) Development of construction progress and management system.
(5) Strengthen fire prevention education to prevent accidents.