What is the installation process of indoor sports solid wood flooring

What is the installation process of indoor sports solid wood flooring

What are the construction processes of sports flooring? With the increasing application of this kind of indoor sports solid wood flooring, it needs to be installed after purchase, which is very important for the installation process, which also directly affects its The use of stability and shock absorption are very important aspects. In order to let everyone know more about this sports solid wood floor, let's take a look at the knowledge of the installation process.

nbfloor


1. Construction conditions

(1) Before the construction of the sports wooden floor, the civil engineering must be completed and the site must be cleaned up to meet the design requirements of the architectural drawings.


(2) After the installation of indoor water, electricity, steam, ventilation, etc. is completed, the water network pipes must pass the pressure test.


(3) The interior decoration roof, ultrasonic, electroacoustic, lighting and other projects are completed.


(4) The ground humidity and equilibrium moisture content are consistent with the outside world.


(5) If there is cross construction, Party A needs to make unified arrangements.


2. Construction preparation

(1) Construction tools and instruments are ready.


(2) Construction materials must be transported to designated locations and stored according to product characteristics.


(3) Check the construction conditions and record the items that do not meet the construction requirements.


(4) Development of construction progress and management system.


(5) Strengthen fire prevention education to prevent accidents.


3. Draw the position line of the keel and the pad.


4. Use a level to detect the height difference of the cement floor at the reference point.


5. Install a 50mm thick pad at the reference point, and the elevation error of the reference pad should not exceed 1mm.


6. Install the keel.


7. Cooperate with the civil engineering unit to install the floor embedded parts.


8. Stagger the multi-layer solid wood fur floor in advance, lay it on the keel, and fasten it with floor nails.


9. Spread the moisture-proof mat on the fur floor.


10. Nail the floor surface layer on the fur floor, requiring a straight line in the longitudinal direction.


11. Use a grinder to polish the surface layer, and a 3-meter ruler is required to measure the height differenceWithin 3mm, the error is large and then polished and leveled.


12. Paint the floor surface, one layer of primer and two layers of topcoat.